Pulled 14 copper runs in Office North, rooms 201–214. Dressed and secured to the tray; ready for terminations tomorrow.
Reroute complete. Two 90s replaced with sweeps, re-strapped to structure, patched and fire-caulked both penetrations.
Terminated 12 drops at IDF-1A, panel B1-P2. Test set ran out of battery — will test first thing tomorrow.
Mechanical added a supply duct on the Floor 2 corridor RCP (rev 3) that lands exactly where AP-2-07 is bracketed. Move the AP 4 ft east to the next tile row, re-pull the service loop, and re-test. Duct hangs next Wednesday — needs to happen before then.